Complex Commercial Litigation

Construction

Disability Rights

E-Commerce

Employment

First Amendment Issues

General Publications

Government Contracts

Professional Liability

Retail Industry Trade Regulation



AMICUS CURIAE BRIEF OF THE ASSOCIATED GENERAL CONTRACTORS OF CALIFORNIA
IN SUPPORT OF RESPONDENT AMELCO ELECTRIC

 

TABLE OF CONTENTS

I. INTRODUCTION

II. THE COURT SHOULD AFFIRM THE COURT OF APPEAL'S HOLDING THAT THE DOCTRINE OF ABANDONMENT APPLIES TO PUBLIC CONSTRUCTION PROJECTS.

A. The Doctrine of Abandonment Is Well-Established Under California Law for Private Construction Projects.

B. The Court Should Decline City's Invitation to Eliminate the Doctrine of Abandonment in California.

C. Applying the Doctrine of Abandonment to Public Construction Projects Is Consistent with Prior Law and Public Policy.

III. CONCLUSION

 

I. INTRODUCTION

AGC urges the Court to affirm the Second Appellate District's holding in this case that the doctrine of abandonment applies to construction contracts with public owners. While this is a question of first impression in California, the State's existing law inevitably leads to the conclusion that the decision below was correct. California law says:

(1) The doctrine of abandonment applies to private construction contracts.

(2) Breaches of public contracts are subject to the same rules and remedies as private contracts.

Putting these two well-established rules of California law together, the doctrine of abandonment should apply to public contracts in this State.

The Court of Appeal's decision below is not only consistent with existing law, it is good public policy. First and foremost, the abandonment doctrine leads to a fair and just result. By making excessive changes after contract award to a project being built to its specifications, an owner may cause several things to happen: it may cause the contractor to be damaged, it may make it impossible for the contractor to make a claim for its damages in accordance with the change order provision in the parties' contract, and it may make it impossible to prove that specific damages were caused by any specific change. The abandonment doctrine allows the contractor to recover all of its damages from the owner when those changes cause all of these things to happen. Further, application of the doctrine to public construction contracts is good public policy because it will provide an incentive for public owners to plan and manage their projects responsibly, which will in turn lead to projects that cost taxpayers less money and better serve their intended public purposes.

The Court should affirm the Court of Appeal's application of abandonment to public contracts as good law and good policy.

II. THE COURT SHOULD AFFIRM THE COURT OF APPEAL'S HOLDING THAT THE DOCTRINE OF ABANDONMENT APPLIES TO PUBLIC CONSTRUCTION PROJECTS

A. The Doctrine of Abandonment Is Well-Established Under California Law for Private Construction Projects.

California courts have expressly recognized the doctrine of abandonment for private construction contracts for almost 50 years. The trilogy of California cases on abandonment of construction contracts -- Opdyke & Butler v. Silver (1952) 111 Cal. App. 2d 912; Daugherty Co. v. Kimberly-Clark Co. (1971) 14 Cal. App. 3d 151; and C. Norman Peterson Co. v. Container Corp. of America (1985) 172 Cal. App. 3d 628 -- have never been questioned by this Court or by any other California court.

1. The only elements of abandonment under California law are (1) the owner imposes
an excessive number of changes and (2) those changes cause the scope of work
under the original contract to be altered

In Peterson, the First Appellate District summarized the requirements for abandonment of construction contracts in California:

[W]hen an owner imposes upon the contractor an excessive number of changes such that it can fairly be said that the scope of the work under the original contract has been altered, an abandonment of contract properly may be found.

Peterson, supra, 172 Cal. App. 3d at 640 (citing Daugherty, supra, 14 Cal. App. 3d at 156, and Opdyke, supra, 111 Cal. App. 2d at 916-919). Thus, Peterson, Opdyke, and Daugherty require that a court find only two things in order to find abandonment: (1) that the number of changes on a project were excessive and (2) that, as a result of these changes, the scope of the work under the original contract has been altered.

The courts in Peterson, Opdyke, and Daugherty all looked at a number of factors to determine whether the two requirements for abandonment are met. As to the first requirement -- an excessive number of changes -- the size, complexity, and expected duration of a project are all relevant considerations. As a result, the California abandonment cases looked at factors such as (1) the number of changes made; (2) the number of changes anticipated when the project started; (3) the size of those changes; and (4) the length of time in which the changes were made. See, Peterson, supra, 172 Cal. App. 3d at 641-642; Opdyke, supra, 111 Cal. App. 2d at 916-918; Daugherty, supra, 14 Cal. App. 3d at 155-156; see also, Dodge v. Harbor Boat Building Co. (1950) 99 Cal. App. 2d 782, 790 (finding that subcontractor was entitled to reasonable value of its work where the prime contractor issued over 100 changes). As to the second requirement -- that the changes caused the scope of the work to be altered -- relevant considerations include the amount of extra work the changes caused the contractor to perform, the extent to which the contractor's work was redesigned, and the magnitude of the extra costs the changes caused the contractor to incur. Peterson, supra, 172 Cal. App. 3d at 641-642; Opdyke, supra, 111 Cal. App. 2d at 916-918; Daugherty, supra, 14 Cal. App. 3d at 155-156. The California abandonment cases have treated these factors as evidence of whether the two requirements for abandonment are met; none of them established any of these factors as additional separate requirements.

2. City tries to expand the elements for abandonment beyond what California law requires.

In attempting to overturn the decision of the lower court, City attempts to impose a variety of new requirements for abandonment. None of these supposed new elements of abandonment are consistent with previous California cases, with decisions in other jurisdictions, or with the sound policy reasons for the doctrine of abandonment.

a. A party does not need to prove actual, mutual intent as a separate element of its abandonment claim.

Although the California cases indicate that mutual intent of the parties to abandon the contract is also an element of abandonment, this is not, in effect, a separate requirement, because it will be implied if the two basic requirements discussed above are et. Peterson, supra, 172 Cal. App. 3d at 643; Opdyke, supra, 111 Cal. App. 2d at 916; Daugherty, supra, 14 Cal. App. 3d at 156. In other words, if an owner issues an excessive number of changes which alter the scope of the work, that alone indicates that the owner intends to abandon the contract. Likewise, if the contractor agrees to go beyond the original scope of work by performing excessive changes directed by the owner, that implies that the contractor intends to abandon the contract. 1/

Opdyke makes this apparent. In that case, the contractor did "not rely upon any evidence of express abandonment"; rather, he argued "that abandonment may be implied from the acts of the parties." 111 Cal. App. 2d at 916. The Third Appellate District affirmed the trial court's judgment for the contractor based on abandonment even though the contractor offered no testimony "that the parties ever expressly agreed to abandon the written contract." Instead, he "simply assumed, according to his testimony, that such abandonment and adoption had been worked by reason of the constant changes, and the constant interference with the work, by [the owner]." Id. at 914. The primary evidence the court looked to for support of the trial court's abandonment finding was testimony that the owner directed numerous changes and the effect those changes had on the project specifications, both of which "evinced a high degree of uncertainty on the part of [the owner] as to what he wanted done." Id. at 916-918. Proof that the parties ignored change order procedures was simply "more evidence" of acts by the parties from which a mutual intent to abandon could be inferred. Id. at 918 ("[t]here was other evidence that should be mentioned, tending to the same conclusion," including the parties' ignoring of the contract's change order provisions) (emphasis added).

Likewise, in Daugherty, the Third Appellate District first discussed the evidence of the amount of the contractor's added costs, the number of changes, the extent of the design changes, the sizes of the individual changes, and the contractor's expectations regarding changes at the time of contacting. 14 Cal. App. 3d at 155-156. The court reversed the trial court's summary judgment for the defendant-owner on the contractor's abandonment claim based on its conclusion that, "because of the tremendous number of changes, there was an issue as to whether the contract had been abandoned by the parties and they proceeded apart from the contract." Id. at 156. In other words, the number of changes alone was sufficient to create a triable issue. Citing Opdyke (supra, 111 Cal. App. 2d at 916), the court reinforced this conclusion with the statement that "[a]abandonment of the contract can occur in instances where the scope of the work when undertaken greatly exceeds that called for under the contract." Id. These conclusions were not qualified. The court did not say, for example, there was a triable issue because there were both excessive changes and the parties ignored the change order procedures in their contract. While the court noted that there was evidence that the parties ignored change order procedures, the court says nothing to indicate that this was necessary to its decision.

Contrary to City's assertions (Opening Brief at p. 16), the California rule as to implied intent to abandon is consistent with the law of most other jurisdictions adopting the abandonment doctrine or the very similar "cardinal change" doctrine. Federal courts, applying the cardinal change doctrine, do not require any proof of intent. 2/ And of the 23 states other than California that recognize either doctrine,3/ only Michigan requires proof of actual intent to abandon. R. M. Taylor, Inc. v. General Motors Corp. (8th Cir. 1999) 187 F.3d 809, cert. denied, 528 U.S. 1159 (2000). For example, the two other states' cases cited by City for the proposition that proof of mutual intent is required (Opening Brief at p. 16) both state that such intent may be implied by the parties' conduct. H.T.C. Corp. v. Olds (Colo. App. 1971) 486 P.2d 463, 466 ("It is the settled and general rule that a contract may be abandoned by mutual consent and that such consent may be implied from the acts and conduct of the parties"); L.K. Comstock & Co., Inc. v. Becon Constr. Co. (E.D. Ky. 1993) 932 F. Supp. 906, 933 ("[p]arties can be shown to have abandoned the contract expressly or implicitly" and "a fact finder can infer abandonment from attendant circumstances and the conduct of the parties"). In H.T.C. Corp., the court discussed the contractor's evidence that the owner ordered "numerous," "extensive" changes and made no mention of the contract's change order process or whether the parties followed it. 486 P.2d at 465-466. It then held that "there was substantial evidence upon which the trial court could base its finding that there had been an abandonment of the original contract." Id. at 467. And in L.K. Comstock, a special master found that the evidence indicated that the extent of the changes ordered was within the parties' expectations at contracting and that the parties did not "conform strictly" with the contract's change order process. 932 F. Supp. at 935. Under those circumstances, the special master found that the evidence of abandonment was insufficient to meet Kentucky's clear and convincing standard of proof. Id. at 936.4/

This makes sense. The number of changes on a project will only be excessive and alter the scope of work if those changes go far beyond the changes the parties anticipated at contracting. As such, issuing such excessive changes shows that the owner intended to abandon the "meeting of the minds" embodied in the contract. This is no different than any other evidence that a party intended to go beyond or outside agreed contract terms, whether they be change order requirements, notice requirements, or any other express or implied terms.

It is this indication of intent to abandon, implied from the excessive number of changes, which distinguishes the California abandonment cases and this case from the cases cited by City for the proposition that contractors cannot recover it they do not comply with the change order provisions in their contracts. Opening Brief at p. 16. In all of the cases cited by City, the owner-directed changes were anticipated by the parties at contracting and were thus not excessive. Under those circumstances, the courts in those cases held the contractors were bound by contractual change order requirements. Huber, Hunt & Nichols, Inc. v. Moore (1977) 67 Cal. App. 3d 278, 301-302; Acoustics, Inc. v. Trepte Constr. Co. (1971) 14 Cal. App. 3d 887; A. Teichert & Son, Inc. v. State (1965) 238 Cal. App. 2d 736, 757-758; see also, Bares v. City of Portola (1954) 124 Cal. App. 2d 813, 819 (contractor failed to prove work performed was "in excess of the performance required of him under the contract"). But the facts in those cases are fundamentally different from the facts here where the changes were so extensive as to affect virtually every part of the work. 5/

b. A party alleging abandonment does not need to prove the date on which abandonment occurred. None of the California abandonment cases require that a party alleging abandonment prove the date on which abandonment occurred.

To the contrary, in Opdyke, the contractor "could fix no definite date" for the event culminating in the abandonment. Supra, 111 Cal. App. 2d at 915. The court found this to be irrelevant, stating that

the precise or even the approximate day the written contract was abandoned and the oral one adopted, if such occurrences took place, is not material.

Id. at 915-916 (emphasis added).

This conclusion is consistent with the nature of abandonment. Abandonment is the culmination of an excessive number of changes, rather than one single event. 6/ There is no particular instant that both parties "decide" to abandon the contract. Rather, it is implied based on the excessive number of changes.

City argues that Amelco was required to prove when the contract was abandoned because the date of the breach is a required element of a plaintiff's prima facie case for breach of contract. This is incorrect. Even in garden variety breach of contract actions, the plaintiff is not required to prove the date, as opposed to the fact, of the alleged breach. Reichert v. General Ins. Co. (1968) 68 Cal. 2d 822, 830 (listing the elements for recovery under breach of contract); see also, 4 B.E. Witkin, California Procedure, "Pleading," ¤ 464 (3rd Ed. 1985). If a plaintiff proves that the defendant breached the contract and caused plaintiff to be damaged, the plaintiff is entitled to recover. Id. There is no reason (and City does not offer one) to apply a more difficult standard in abandonment claims; to the contrary, since the date of abandonment would in most cases be more difficult to prove than the date of breach in other cases, and since that difficulty is created by the defendant-owner, there is a good reason to apply a less difficult standard for proving abandonment than traditional breach.

Adding a requirement, as City urges, that an abandonment plaintiff prove when the abandonment occurred is contrary to the rule in California that a plaintiff must prove the fact of damage with certainty but need not prove the amount of damage with certainty. Zinn v. Ex-Cell-O Corp. (1944) 24 Cal. 2d 290, 297-298; California Lettuce Growers v. Union Sugar Co. (1955) 45 Cal. 2d 474, 486-487; Cassinos v. Union Oil Co. (1993) 14 Cal. App. 4th 1770, 1784. If an abandonment occurred and damaged Amelco (as it proved at trial), when that abandonment occurred is potentially relevant only to the amount of recoverable damages. But given the jury's unequivocal finding that City breached the contract, Amelco was entitled to (and did in fact) use less specific methods of establishing its damages.

Allowing a contractor demonstrating abandonment to recover damages without imposing an additional requirement that it prove when the abandonment occurred does not mean that the contractor will receive a windfall. There is no indication that Amelco received such a windfall here. Amelco did not seek all of its increased costs but rather presented a modified total cost claim. 7/ The modified total cost approach requires reduction of damages to account for costs for which the contractor is responsible, whether as a result of underbidding or its own performance mistakes. The jury here was instructed to award only those damages which were attributable to the City's breach. The jury's damage award -- reduced from even Amelco's proposed modified total cost calculation -- demonstrates that the jury took seriously its obligation to award the damages which it determined the City had caused and nothing more.

c. A party alleging abandonment does not need to prove a change in the nature of the final construction product.

Under the California cases, abandonment will be found where the number of changes on a project are so excessive as to change the scope of the work. Peterson, supra, 172 Cal. App. 3d at 640 (citing Daugherty, supra, 14 Cal. App. 3d at 156, and Opdyke, supra, 111 Cal. App. 2d at 916-919). The rule stated by these cases does not mean, as City urges (Opening Brief at p. 18), that the changes must result in an entirely different end product. It does not mean that a contractor has to prove it originally contracted to build a shack and ended up building the Taj Mahal.

Instead, as the discussions in Peterson and Daugherty demonstrate, the extent of alteration in the work, rather than in the nature of the final construction product, are the relevant consideration in determining whether changes effect an abandonment of a construction contract. In Peterson, supra, 172 Cal. App. 3d at 637, the owner made numerous changes to the plans for a mill modernization project, and, while the court discussed the loss of productivity and increase in costs that resulted, it does not even mention the difference, if any, between the mill as specified in the original contract and as modified under the changed specifications. Likewise, in Daugherty, supra, 14 Cal. App. 3d at 156, the court discussed the number of changes in the plans for a mill construction and the resulting increase in the contractor's costs. The only mention of the changes' effect on the mill itself was a reference to "upgrading the mechanical and electrical installation." Id. In neither of these cases is there any indication that the court considered a change in the nature of the final construction product necessary to show that there was an abandonment, so long as the work performed differed materially from the work the parties anticipated.

In addition, federal courts apply the similar cardinal change doctrine in cases where the end product is substantially similar to that which the contractor originally contracted to build. In Edward R. Marden Corp. v. United States (Ct. Cl. 1971) 442 F.2d 364, 369-370, for example, the contractor entered into a contract with the US Navy to build an aircraft maintenance hangar in accordance with specifications issued by the Navy. After the contractor built the hangar, it collapsed due to a defect in the construction sequence called for in the specifications. 8/ The Navy ordered the contractor to reconstruct the hangar. Clearly, the scope of the contractor's work had changed, even though the final construction product had not. Under those circumstances, the court found a cardinal change:

In the present case the reconstructed hangar was, presumably, the identical hangar called for in the original specifications. In other words, in directing reconstruction of the hangar, the Government did not alter the design or other physical characteristics of the structure. We do not view this as a crucial difference, however. Where a cardinal change is concerned, it is the entire undertaking of the contractor, rather than the product, to which we look.

442 F.2d at 370 (emphasis added).

Air-A-Plane Corp. v. United States (CT CL 1969) 408 F.2d 1030, a case from the Court of Claims on which City relies, makes the same point. There, a contractor had entered into a fixed price contract with the Army Chemical Corps to build smoke generators. During performance, the Army made "a large number of changes" in the contractor's work, which increased the contractor's costs. Id. at 1031-1032. After the Army's contracting officer denied a substantial portion of the contractor's claim for an equitable adjustment in the contract price to account for the impacts these changes had on its costs, the contractor challenged that denial in the Armed Services Board of Contract Appeals. The Board found that the contractor "in bidding on the contract, had not anticipated that any substantial number of changes would be ordered." Id. at 1031. It also found that the changes were so numerous "that the contract took on the aspect of a design or development contract." Id. at 1032. As was true of Amelco's work for City in this case, portions of the contractor's work in Air-A-Plane were changed several times, and others, while not themselves changed, were affected by changes to other portions of the work. And it found that "[t]he frequency and nature of the changes were disruptive of [the contractor's] production." Despite those findings, the Board held that the contractor's recovery was limited to the adjustments made under the contract's changes provision. The contractor appealed to the United States Court of Claims, alleging "that [the Army] breached the contract because the changes imposed amounted in toto to a cardinal change, beyond the scope of the Changes article." Id.

In its opinion, the Court of Claims stated the basic standard for a cardinal change: "whether the modified job Ôwas essentially the same work as the parties bargained for when the contract was awarded.'" Id. at 1033 (citations omitted). Whether there was a cardinal change in a particular case

can be resolved only "by considering the totality of the change and this requires recourse to its magnitude as well as its quality." [citations omitted] . . . "There is no exact formula * * * . Each case must be analyzed on its own facts and in light of its own circumstances, giving just consideration to the magnitude and quality of the changes ordered and their cumulative effect upon the project as a whole."

Id. (quoting Wunderlich Contracting Co. v. United States (CT CL 1965) 351 F.2d 956, 966). Applying these general standards to the facts, as found by the Board below, the Court of Claims stated "that the [contractor's] claim of a cardinal change is very substantial and far from frivolous." Id. The court remanded, instructing the Board to hear contractor's cardinal change claim on its merits. Id. at 1033, 1038. In so doing, the court again made clear that the extent of change necessary for a cardinal change may occur as a result of the number of changes, not just as a result of a change in the nature of the end product.

In any event, even if a change in the final product were a requirement for abandonment, Amelco would have met its burden. Amelco had a contract directly with City to build the electrical system for the City's civic center. Substantial evidence was presented that this system was significantly altered as a result of the excessive changes directed by City. The evidence established that City changed every part of the electrical work at least once, it changed some parts many times, and it changed other areas of work which impacted the electrical work. See, Amelco Electric v. The City of Thousand Oaks (2000) 82 Cal. App. 4th 373, 380-381. Such a situation is more than sufficient to show that City and Amelco abandoned their contract for the electrical system, even if, as City contends, "[t]he size, height, number of floors, uses and location of the building" in which Amelco installed the electrical system "never changed" (quoting Reply Brief at p. 18).

d. A party alleging abandonment does not need to prove it complied with contractual notice requirements.

Requiring a contractor to prove that it complied with notice provisions in its contract, as City urges here, would be inconsistent with California authority that a party that breaches a contract is not entitled to rely on provisions in that contract to require the non-breaching party to provide it notice of its own breach. D.A. Parrish & Sons v. County Sanitation Dist. (1959) 174 Cal. App. 2d 406, 414; Hawley v. Orange County Flood Control Dist. (1963) 211 Cal. App. 2d 708, 715. City argues in its Opening Brief (at pp. 20-21), that the Court of Appeal in this case misread DA Parrish, but it is City that misreads that case. In DA Parrish, the court addressed the question of whether a notice requirement in a contract provision for extra work required the contractor to provide notice of its damages caused by delays arising from defects in the owner's specifications. The court provided two separate grounds for its answer in the negative: first, the clause dealt with extra work, not delays, so it did not apply to the contractor's claim, and, second, forfeiture clauses like the notice clause at issue had "been interpreted by this court not to apply to claims arising from breaches of the contract caused by the other party." 174 Cal. App. 2d at 414.

The discussion of Parrish in Hawley, supra, confirms that it is City, rather than the Court of Appeal below, that misreads Parrish. The Hawley court observed:

The Parrish case itself held that a requirement for 10-day notice on claims for extra work did not apply to claims for extra work caused by the public body's breach of contract through that body's errors in the layout of sewer line which in effect amounted to breach of contract, causing unconscionable delay through the necessity of laying out a new course.

211 Cal. App. 2d at 715.

Holding Amelco to the notice requirements in the change order provision in its contract with City here would be contrary to DA Parrish. The City's actions in ordering an excessive number of changes so as to alter the nature of the work undertaken amounts to a breach of the City's implied warranty that the specifications were adequate. The City cannot rely on the notice requirements in the contract's changes clause to avoid the consequences of its own breach.

B. The Court Should Decline City's Invitation to Eliminate the Doctrine of Abandonment in California.

1. The abandonment doctrine is consistent with other rules of contract interpretation.

The central tenet of contract interpretation is giving effect to what the parties intended. Civil Code ¤ 1636. This often requires courts to go beyond express contract language to deal with situations beyond the parties' anticipation at the time of contracting. Hawley, supra, 211 Cal. App. 2d at 713-714 ("While the intention of the parties is derived initially from the language used in the written contract, ÔThe words, phrases and sentences employed are to be construed in the light of the expressed objectives and fundamental purposes of the parties to the agreement' [citation omitted]"). In such cases, courts will imply reasonable terms on the theory that, had the parties anticipated the unanticipated event, they most likely would have included a reasonable term to deal with that event. Cf. Tonkin Constr. Co. v. County of Humboldt (1987) 188 Cal. App. 3d 828, 832 ("a contract includes not only the terms that have been expressly stated but those implied provisions indispensable to effectuate the intention of the parties") (citing Civil Code ¤ 1656; Sacramento Navigation Co. v. Salz (1927) 273 US 326, 329).

For example, where public construction contracts contain "no damages for delay" provisions stating that the contractor is not entitled to recover any damages resulting from owner-caused delays, courts have implied a reasonable limitation on such provisions, both before and after the Legislature acted to make such limitations statutory in Public Contract Code ¤ 7102. In cases where the delay is extreme, such that it is beyond what the parties contemplated when they entered into their contract, courts have awarded damages to contractors, despite the no damages for delay provisions in their contracts. Howard Contracting, Inc. v. G. A. MacDonald Constr. Co., Inc. (1998) 71 Cal. App. 4th 38, 50-51 (rejecting argument by cross-defendant/appellant city that clause precluded contractor recovery of damages caused by city's breach of contract) (citing Public Contract Code ¤ 7102); McGuire & Hester v. City and County of San Francisco (1952) 113 Cal. App. 2d 186, 191 (same result before ¤ 7102 was enacted); Milovich v. City of Los Angeles (1941) 42 Cal. App. 2d 364, 373 (same).

Abandonment is no different. Change order provisions deal with the changes the parties anticipate at contracting. Where the number of those changes goes so far beyond that which the parties expected that the scope of the contract work has been altered, courts will apply the abandonment doctrine to imply reasonable limits on the applicability of those change order provisions and allow the contractor to recover the cumulative costs increased by those changes.

2. Public policy supports the abandonment doctrine.

The abandonment doctrine leads to fair and just results. When an owner directs an excessive number of changes that cause a contractor to incur added costs which neither party anticipated at the time of contracting, the doctrine puts the responsibility for those added costs on the party that caused them. When the contractor incurs those added costs cumulatively, such that they cannot be identified or measured accurately at or near the time they occur, the doctrine prevents the owner, as the party that caused the added costs, from escaping liability by invoking change order or notice procedures in the contract. And when the excessive number of those changes make it difficult (or impossible) for the contractor to prove the amount of added costs with certainty, the doctrine prevents the owner, as the party who caused those difficulties, from escaping liability by arguing the contractor cannot meet its burden of proof as to the precise dollar value of those damages.

The doctrine recognizes some undeniable realities in construction. On virtually all construction contracts, the parties anticipate at the time of contracting (1) that the owner knows what it wants and (2) that, when the owner provides specifications, it has taken reasonable steps to ensure that they are correct and complete. When an owner undertakes the design aspect of the work, it impliedly warrants that its design is not defective. Souza & McCue Constr. Co. v. Superior Court (1962) 57 Cal. 2d 508, 510; see also, United States v. Spearin (1918) 248 US 132, 136-137. The contractor is entitled to rely on that warranty. The doctrine of abandonment recognizes this and provides an effective means of making the owner responsible for all of the added costs caused by its breach of that warranty.

In addition, most construction projects are extremely complex, involving many different trades performing work interconnected with the work of others. On the normal job, a contractor can anticipate that the owner may direct some level of changes in the work design, materials or schedule, and is equipped to determine the costs of such changes close to the time in which they occur. In unusual cases, however, the alterations in the work may occur to an extent which the parties did not, and could not, have anticipated in their contract. That may be either because the alterations required are very different in nature from the changes that normally occur on similar projects or because they are far more numerous than parties reasonably would expect. Particularly where there is an extraordinary number of changes, inefficiencies occur which increase a contractor's costs. But this cost increase may only be detected long after the inefficiencies were first created and, even then, the amount of the increase is often impossible to determine with certainty. Because the excessive number of changes was not anticipated at contracting, the change order provisions in the parties' contract were not designed to deal with the situation and to compensate the contractor fairly. The owner who causes the excessive number of changes should bear the additional costs not addressed by the contract procedures. In addition, in many cases the changes ordered by the owner provide additional value to the owner; it would be unfair to allow owners to enjoy that additional value without paying for it. The doctrine of abandonment recognizes all of this and puts the responsibility for added costs on the owner.

City argues that allowing abandonment claims will encourage contractors to submit artificially low bids (Opening Brief at 14). But this contention ignores that abandonment is difficult to prove and, as a result, very rare. A contractor that underbids its jobs with the expectation that the owner will order an excessive number of changes that alter the scope of work will be out of business quickly. It is no coincidence that there are only three reported decisions applying the abandonment doctrine in California over the past 50 years. The test fashioned by California courts for recovery under that doctrine is very hard to meet, and no reasonable contractor would bid on a job expecting to be able to rely on the doctrine later.

3. At least 23 other states, the District of Columbia, and federal courts recognize the abandonment doctrine in some form.

Whether they call it "abandonment," "cardinal change," or something else, at least 23 other states, the District of Columbia, and the Federal courts, allow contractors to recover their added costs caused by excessive, owner-directed changes which alter the scope of the work under the parties' original contract. 9/ Only one state, Mississippi, has expressly declined to adopt this approach. Litton Systems, Inc. v. Frigitemp Corp. (S.D. Miss. 1985) 613 F. Supp. 1377. Far from being a minority view, as City suggests,10/ California law is consistent with almost every one of the many other jurisdictions which have considered abandonment.

C. Applying the Doctrine of Abandonment to Public Construction Projects Is Consistent with Prior Law and Public Policy.

1. It is well-established under California law that public owners are subject to liability for breach of contract the same as private parties.

Although construction contracts with public owners are subject to statutory competitive bidding requirements, once a public owner awards a contract in compliance with those requirements, "it is liable for a breach of its agreement in like manner as an individual." Souza, supra, 57 Cal. 2d at 510; see also, Bilardi Constr., Inc. v. Spencer (1970) 6 Cal. App. 3d 771, 774 (contract provision limiting city's liability under contract to money in special fund did not limit amount of damages contractor could recover for city's breach of contract); Tonkin Constr. Co. v. County of Humboldt (1987) 188 Cal. App. 3d 828, 831-832; 1 B.E. Witkin, Summary of California Law, "Contracts," ¤¤ 81, 87 (9th Ed. 1987). There are two reasons for this: (1) competitive bidding laws deal with procurement, rather than performance, of contracts, and (2) when a public entity enters into a contract it waives sovereign immunity for liability under the contract.

Competitive bidding requirements do not affect the rules for determining what is a breach of contract or what remedies are available for breach. Shea-Kaiser-Lockheed-Healy v. Dept. of Water & Power (1977) 73 Cal. App. 3d 679, 684. Rather, "such requirements apply only to the procedure by which the price of goods purchased by a public entity is set." Id. (citing Miller v. McKinnon (1942) 20 Cal. 2d 83, 87-88). In Shea, the Department of Water & Power ("DWP") made an argument similar to one City makes here. The trial court had found that the DWP breached its contract with Shea and held the DWP liable for the value of materials Shea delivered to it under their contract. On appeal, the DWP argued that the trial court's damage award violated competitive bidding laws because the award was based on quasi-contract or implied contract. The Second Appellate District rejected this argument stating that competitive bidding requirements were "irrelevant to the propriety of the damage awards before [the court]." Id. (emphasis added). Since court awards of damages for breach are not made "pursuant to contract," they "are not precluded by competitive bidding requirements." Id.

Sovereign immunity also does not prevent a contractor under contract to a public owner from recovering damages caused by the public owner's breach of contract, just as it could under a construction contract with a private owner. Souza, supra, 57 Cal. 2d at 510; 1 B.E. Witkin, Summary of California Law, "Contracts," ¤ 87 (9th Ed. 1987).

A contractor has the same right to recover for breach of the owner's implied warranty that its plans and specifications are correct and complete whether that owner is public or private. Souza, supra, 57 Cal. 2d at 510-511; Warner Constr. Corp. v. City of Los Angeles (1970) 2 Cal. 3d 285, 293-294 (quoting Souza); E.H. Morrill Co. v. State (1967) 65 Cal. 2d 787, 791; Tonkin Constr., supra, 188 Cal. App. 3d at 832. Just as with private owners, public owners warrant that the specifications they issue are correct, and contractors are entitled to rely on that warranty. Id. In the context of public contracts, contractor may reasonably rely on the correctness of the owner's specifications in determining its costs as the basis for its bid. Id. And, to the extent that the specifications prove to be incorrect or incomplete, the public owner, like private owners, is liable for the cost of extra work which is necessitated by the owner's breach of warranty. Id.

Unlike the contracts involved in many of the cases cited by City (Opening Brief at 31-34), there is no contention here that the contract awarded by City to Amelco in this case violated any competitive bidding laws 11/ or that the parties agreed to a modification of the contract in violation of those laws. 12/ As such, the defense available to the public owners in those cases, i.e., that the contracts in those cases were void (i.e., treated as if they never existed), are not available to City in this case, and City is subject to the same contract remedy rules that apply to contracts between private parties. 13/

2. Many of the other jurisdictions that have adopted abandonment doctrines have applied those doctrines to public construction contracts.

Amelco cites a number of other state and federal cases which apply the abandonment doctrine or something similar to construction contracts (Amelco Brief at pp. 34-35, n. 15-17). It is noteworthy that the cited cases from five different states and all of the federal cases, involve public contracts. Arizona, Arkansas, New York, Oregon, and Washington courts have all decided that abandonment applies to contracts with public owners. 14/ And, of course, the similar federal doctrine of cardinal change was invented for federal government contracts. City has not cited, and AGC has been unable to locate, a single reported case from any jurisdiction refusing to apply the abandonment doctrine to public contracts. 15/

E.W. Johnson, supra, 264 Ark. 523, is typical of the consistent application of the abandonment theory to public contracts. There, a city had directed numerous changes (id. At 528, n. 2), which the trial court found constituted a breach of contract (id. At 532-533). On appeal, the city argued "that the contract permits the owner to make changes in the work of the contractor without invalidating the contract." Id. at 533. The Arkansas Supreme Court was unpersuaded and affirmed the trial court holding that the city "breached the warranty of the plans and specifications submitted to the [contractor] resulting in cardinal changes in the contract." Id. at 525, 535.

3. Applying abandonment to public projects serves the same public policy objectives served by its application to private projects and additional public policy objectives as well.

Application of the abandonment doctrine in cases like this one would serve several important public policy objectives. First, applying the doctrine of abandonment in public construction would lead to fair and just results. It is just as fair to hold a public owner as a private owner responsible for the added costs it causes a contractor to incur by directing an excessive number of changes which neither party anticipated at the time of contracting. And it is just as fair to prevent a public owner from escaping liability simply because its own actions have made it difficult or impossible for the contractor to identify and measure its resulting cost increases in compliance with the change order and notice provisions in the contract or to prove the amount of its added costs with certainty. Justice requires application of the abandonment doctrine for public contracts even more so than for private ones because contractors are precluded by law (Public Contract Code section 1104) from designing public projects. As a result, the contractor on a public contract cannot be said to have accepted the risks associated with declining design responsibility; instead, the contractor must rely on the accuracy of the public owner's design and plans in bidding the project.

Second, the abandonment doctrine encourages responsible planning of projects by public owners, which in turn leads to a better product at a lower price. It lets owners know that they will bear all of the costs that result from their ordering excessive changes altering the scope of their contractors' work. This rule provides a strong disincentive to public owners from putting projects out to bid without planning those projects carefully. Such careful planning will, in turn, lead to public works that are built more efficiently, with fewer delays, and at a lower cost. It will also lead to better thought out projects that more effectively meet the public purposes for which they were intended. Finally, by discouraging public owners from putting contracts out for bid with incomplete plans, the abandonment doctrine supports the goals of the competitive bidding statutes by fostering more meaningful competition for public contracts.

Similarly, once public projects are underway, the potential application of the abandonment doctrine to those projects will encourage public owners to manage those projects responsibly. When deciding whether to order wholesale changes, the public owner will know that the more additional changes it directs the more likely it will alter the scope of the contractor's work beyond that in the original contract, and it will know that it may have to pay for added costs associated with those changes, even if they are determined outside of change order procedures. Armed with this knowledge, owners can weigh the benefits of the change with its true costs and make a reasoned decision of whether the public work would benefit from widespread changes on a project.

III. CONCLUSION

Under the doctrine of abandonment, California, like many other jurisdictions, allows construction contractors to recover their damages when an owner issues an excessive number of changes that alter the scope of the contractor's work. Because some of these damages are cumulative, California does not require contractors to comply with contract notice or change order provisions as a prerequisite to their recovery. And because these damages cannot be attributed to any particular change, California allows contractors to prove those damages indirectly (for example, by using the modified total cost method). All of this leads to a fair and just result by making the party that caused the additional costs liable for those costs.

Although California has not yet applied the abandonment doctrine to public construction contracts, such an application is consistent with California law in similar contexts and is good public policy. California applies the same rules of contract interpretation and remedies to both public and private owners. This includes implying reasonable limits on the application of contract clauses when circumstances are different than what the parties anticipated at contracting. And, it is just as fair to hold a public owner responsible for added costs caused by its excessive changes as it is to do so for private owners. Finally, applying the abandonment doctrine to public owners serves an additional public interest by encouraging public owners to carefully plan and manage public construction, which will lead to lower costs and better products.

In this case, the jury found that City damaged Amelco by ordering an excessive number of changes and substantially altering the scope of Amelco's work. These damages were not adequately accounted for in the change orders made on the project. The Court of Appeal affirmed the award, holding that it was consistent with prior California abandonment and public contract decisions. Now, this Court should do the same.

Dated: May __, 2001

Respectfully submitted,
ROGERS, JOSEPH, O'DONNELL & PHILLIPS
Neil H. O'Donnell
Aaron P. Silberman
Attorneys for Amicus Curiae, the Associated General Contractors of California

Footnotes

  1. See, e.g., Hayden v. Astoria (1915) 74 Or. 525, 533 (changes which substantially increased portions of the contractor's work "must be considered as not being within the contemplation of the parties at [contracting]" and, therefore, in regard to the project as constructed, "there was no meeting of the minds of the parties as to the amount of compensation"); H.T.C. Corp. v. Olds (Colo. App. 1971) 486 P.2d 463, 466 ("A contract will be treated as abandoned when the acts of one party, inconsistent with its existence, are acquiesced in by another") (citations, of Nebraska and Oklahoma cases, omitted). Back
  2. California courts look to federal decisions as persuasive authority in public construction cases. See, e.g., Pacific Architects Collaborative v. California (1979) 100 Cal. App. 3d 110, 125. Back
  3. See cases cited in Opening Brief at p. 16; Amelco Brief at pp. 34-35, n. 15-17; and Reply Brief at pp. 16-17, n.2; see also, Nat Harrison Assoc., Inc. v. Gulf States Utilities Co. (5th Cir. 1974) 491 F.2d 578, 583, reh'g denied, 493 F.2d 1405 (applying Louisiana law); Oberer Constr. Co. v. Park Plaza, Inc. (Oh. Ct. App. 1961) 179 N.E.2d 168, 171; Fuller Co. v. Brown Minneapolis Tank & Fabricating Co. (E.D. Pa. 1987) 678 F. Supp. 506, 509 (applying Minnesota law); Nat'l Environmental Service Co., Inc. v. Hompeplace Homes, Inc. (Tex. App. 1998) 961 S.W. 2d 632, 635. The states other than California to adopt abandonment or cardinal change doctrine are (1) Alabama, (2) Arizona, (3) Arkansas, (4) Colorado, (5) Indiana, (6) Kentucky, (7) Louisiana, (8) Maine, (9) Maryland, (10) Michigan, (11) Minnesota, (12) Missouri, (13) New York, (14) North Dakota, (15) Ohio, (16) Oklahoma, (17) Oregon, (18) Rhode Island, (19) Texas, (20) Utah, (21) Washington, (22) Wisconsin, and (23) Wyoming. The District of Columbia has also implicitly recognized the abandonment doctrine. Blake Constr. Co., Inc. v. C. J. Coakley Co., Inc. (D.C. CT App. 1981) 431 A.2d 569, 578-579 (subcontractor entitled to recover for damages from delays caused by general contractor not contemplated by the parties at contracting or "amounting to an abandonment of the contract"). Back
  4. Contrary to City's assertion, neither L.K. Comstock nor any other Kentucky case holds that "compliance with the change order process negates a claim of abandonment" (quoting Opening Brief at p. 16). Back
  5. Even if Amelco had been required to prove that the parties ignored the change order procedures in their contract to show that the parties intended to abandon the contract, Amelco met its burden here. It submitted substantial evidence at trial that, due to City's excessive changes, City directed Amelco to do its work on a "price and proceed" basis, i.e., perform changes in the work before change ordered could be negotiated. See, Amelco Brief at p. 14. Back
  6. A California court recognized, albeit outside the abandonment context, that a contractor may incur added costs due to a public owner's ordering numerous changes which cumulatively alter the character of the contractor's work. State of California v. Guy F. Atkinson Co. (1986) 187 Cal. App. 3d 25, 32. In Atkinson, the trial court confirmed an arbitration award to a contractor, in which the arbitrator stated: "There were cumulative effects of all of the ordered changes. It is not feasible or possible to separately identify or measure those costs which were incurred by Atkinson as a result of the actions of the State." Id. at 29 n.2. The Court of Appeal affirmed. Back
  7. AGC agrees with Amelco that substantial precedent indicates that the total cost method of calculating damages may be used in appropriate circumstances. City of Salinas v. Souza & McCue Constr. Co. (1967) 66 Cal. 2d 217, 225; Atkinson, supra, 187 Cal. App. Back
  8. The plans failed to require that "the tie rods had to be installed before the arches were released on the buttresses." 442 F. Supp. at 370. Back
  9. See, footnote 2, infra. Back
  10. Opening Brief at p. 16 ("Few other states recognize the abandonment doctrine"). Back
  11. Miller v. McKinnon (1942) 20 Cal. 2d 83, 87-88 (Court voided contract because public owner did not put contract out for competitive bid); South Bay Senior Housing v. City of Hawthorne (1997) 56 Cal. App. 4th 1231, 1235 (same). Back
  12. Paterson v. Bd of Trustees (1958) 157 Cal. App. 2d 811, 818-819 (Court voided contract modification agreed to by a public official in excess of his authority); Greer v. Hitchcock (1969) 271 Cal. App. 2d 334, 336 (same). Back
  13. Two cases cited by City -- Zottman v. City and County of San Francisco (1862) 20 Cal. 96, 99-102, which was decided by this Court almost 140 years ago, and Contra Costa Constr. Co. v. Daly City (1920) 48 Cal. App. 622, which was decided by the First Appellate District 65 years before Peterson -- involve claims for extra work ordered on a valid public contract but contain no discussion about whether the ordered changes were excessive or altered the scope of the contract work. To the extent that the Court finds that either of these cases applies to abandonment situations, like those found here and in the California abandonment cases, AGC submits that Zottman and Contra Costa should be overruled. Back
  14. See, e.g., County of Greenlee v. Webster (1923) 25 Ariz. 183; Housing Authority of the City of Texarkana, Arkansas v. E.W. Johnson Constr. Co. (1978) 264 Ark. 523; Westcott v. State (1942) 36 N.Y.S.2d 23; Hayden, supra, 74 Or. 525; and Kieburtz v. City of Seattle (1915) 84 Wash. 196; see also, Scherer Construction, LLC v. Hedquist Construction, Inc. (Wyo. 2001) 18 P.3d 645, 656 (assumes, without deciding, that cardinal doctrine applies to public owners). Back
  15. As Amelco notes in its brief (at p. 35), the one jurisdiction to reject the doctrine of abandonment generally is Mississippi. The case Amelco cites -- Litton Systems, Inc. v. Frigitemp Corp. (1985) 613 F. Supp 1377 -- involves a private project. Back


Back to top



Back to Construction Publications