|
Procedural Differences in Post-Award Protests
at the Court of Federal Claims and the U.S. General Accounting Office
Presented to the 41st Western Briefing Conference
on Government Contracts
By Allen Samelson, David Innis, and Anthony
Bedwell-Coll.
In 1997 the Court of Federal Claims became a new option
for disappointed bidders seeking a forum to resolve disputed contract
awards. See Administrative Dispute Resolution Act of 1996, P.L.104-320,
28 U.S.C. Û 1491(b)(1). In the short period that the Court has received
this new jurisdiction over post-award protests, it has promulgated a set
of specific procedural rules governing bid protests and has published
a number of significant opinions governing both procedural and substantive
aspects of bid protest litigation. As a result, a number of factors have
emerged that may help a government contractor decide whether to file a
post-award protest in the Court of Federal Claims or at the General Accounting
Office (GAO). This article briefly describes the rules governing protests
filed at the Court of Federal Claims and explores some of the principal
factors that may influence a choice of forum decision.
I. COURT
OF FEDERAL CLAIMS BID PROTEST PROCEDURES
By issuance of General Order No. 38 issued on May
7, 1998, the Court of Federal Claims adopted specific procedures for the
disposition of both pre-award and post-award protest cases. See R. Ct.
Fed. Cl. Gen. Order 38 (available at www.contracts.ogc.doc.gov/fedcl/docs/order38.html).
These procedures supplement the Rules of the Court of Federal Claims,
which are based upon the Federal Rules of Civil Procedure and otherwise
remain fully applicable to bid protest cases. See Gen. Order 38
App. I õ 1; see also R. Ct. Fed. Cl. 1.
The basic procedural progression of a Court of Federal
Claims bid protest is as follows:
(1) the protester provides at least 24 hour prior
notice of filing to the Department of Justice Commercial Litigation
Branch, the clerk of the Court of Federal Claims, the procuring agency
contracting officer, and the apparently successful bidder or offeror
(Gen. Order 38 App. I õõ 2 &3);
(2) a complaint is filed together with motions for
(a) leave to file under seal, (b) a protective order, (c) and temporary
restraining order and preliminary injunction (all of which should be
accompanied by supporting papers and redacted copies) (Gen. Order 38
App. I õõ 4, 9, 12);
(3) the Court holds an initial status conference
"as soon as practicable after the filing of the Complaint" to address
"relevant issues including, but not limited to, the following: (a) Identification
of the interested parties; (b) Requests for temporary or preliminary
injunctive relief, if filed . . .; (c) The content of a protective order,
if requested by one or more of the parties; (d) The content and time
for filing of the administrative record; (e) Whether it may be appropriate
to supplement the administrative record; and (f) The nature of and schedule
for further proceedings." (Gen. Order 38 õ 8);
(4) the parties engage in discovery and motion practice,
such as motions to dismiss for lack of jurisdiction, insufficiency of
process, or failure to state claim upon which relief can be granted;
motions to intervene; and motions to be admitted to a protective order;
and
(5) the case is resolved by summary judgement or
an adjudication on the merits.
This brief summary shows that the procedure for bid
protests conducted by the Court of Federal Claims is largely regulated
by the Court following filing of the complaint. The resolution on the
merits is reached pursuant to a time frame determined by the court and
the complexity of the issues involved in the protest. In contrast, the
GAO's bid protest procedures are described in much greater detail in GAO's
regulations, see 41 C.F.R. Part 21, and the GAO must issue a decision
within 100 days of receiving a timely protest, 31 U.S.C. Û 3554(a)(1).
Relative to the GAO, at the Court of Federal Claims it is more difficult
to predict with certainty either the schedule or the precise scope of
the process that will be followed at the Court.
II. TIME FOR FILING BID PROTESTS
Unlike the GAO, which has very strict -- and short -- time
deadlines for filing a protest (see 4 CFR Û 21.2(a)), the Court of Federal
Claims has no specific time limit for filing post-award claims for relief.
Thus, the Court of Federal Claims provides more time for a protester to
file a post-award protest than does the GAO. However, a protester should
never unduly delay filing a protest at the Court of Federal Claims, since
the later a protester files, the smaller are the protester's chances of
getting a temporary restraining order or a preliminary injunction. See
Ralph C. Nash, et al., Competitive Negotiation: The Source Selection
Process 874 (2nd ed. 1999).
III. SUSPENSION OF THE AWARD AND CONTRACT
PERFORMANCE
By statute (31 U.S.C. Û 3553) and regulation (FAR
33.104(c)), the procuring agency is required to suspend or terminate the
awarded contract if a protest is filed at the GAO within the time limits
prescribed. The agency may override a "stay" if the requisite findings
are made. See FAR 33.104(c)(2). At the Court of Federal Claims,
a stay is by no means "automatic." More effort is required in the Court
of Federal Claims than in the GAO to obtain a stay of the procurement.
The Rules of the Court of Federal Claims require a
party to file a motion for a temporary restraining order and preliminary
injunction along with the complaint to obtain a stay of contract performance.
In ruling on these motions, the Court of Federal Claims will examine the
following factors:
(1) the likelihood of plaintiff's success on the
merits of its complaint; (2) whether plaintiff will suffer irreparable
harm if the procurement is not enjoined; (3) whether the balance of
hardships tips in the plaintiff's favor; and (4) whether a preliminary
injunction will be contrary to the public interest.
DSD Laboratories, Inc. v. United States, 46
Fed. Cl. 467, 480 (2000). When a stay of the procurement is sought, the
Court will address a number of issues at the initial status conference.
These include:
(a) Whether and to what extent, absent temporary
or preliminary injunctive relief, the Court's ability to afford
effective final relief is likely to be prejudiced;
(b) If a temporary restraining order has been
requested, whether the government will agree to withhold award or
suspend performance pending a hearing on the motion for preliminary
injunction;
(c) If a preliminary injunction has been requested,
whether the government will agree to withhold award or suspend performance
pending a final decision on the merits;
(d) An appropriate schedule for completion of
the briefing on any motion for a preliminary injunction;
(e) The security requirements of Rule 65(c);
and
(f) Whether the hearing on the preliminary injunction
should be consolidated with a final hearing on the merits.
Gen. Order 38 õ 10. Although the Court of Federal
Claims is not subject to the GAO's mandatory stay provision, it has recently
assumed a role in interpreting that provision. When a procuring agency
elects to override the mandatory stay at the GAO, the protester may challenge
that override by seeking injunctive relief at the Court of Federal Claims.
Ramcor Services Group, Inc. v. United States, 185 F.3d 1286 (Fed.
Cir. 1999).
IV. PROTECTION OF PROPRIETARY MATERIALS
The Court of Federal Claims requires a motion for
a protective order before it will prevent the public release of proprietary
materials involved in a protest. A simple request is all that is necessary
at the GAO, which also may issue a protective order on its own initiative.
4 CFR Û 21.4. At the Court, a motion must be filed with the complaint,
along with a redacted version of all papers and a motion for leave to
file under seal should the moving papers themselves contain sensitive
information. The motion will be addressed at the Court's initial status
conference. Gen. Order 38 õ 8(c). The decision whether or not to issue
a protective order is within the Court's discretion. Gen. Order 38 õ 12(a).
Although the Court of Federal Claims provides a sample protective order,
the Bid Protest Procedures warn that individual judges and the parties
themselves may want to amend the sample order to suit the needs of specific
cases or their individual preferences. Gen. Order 38 õ 12(b).
The GAO generally respects the wishes of the parties
with respect to proposal information deemed to be proprietary. In contrast,
a bid protester at the Court of Federal Claims must be aware of the strong
public policy in favor of making all proceedings before the Court of Federal
Claims open to the public. One of the statutes establishing the Court
of Federal Claims provides that "[a]ll decisions of the Court of Federal
Claims shall be preserved and open to inspection." 28 U.S.C. Û 174(b).
Indeed, in one decision the Court ordered -- over the unanimous objections
of the parties -- proprietary and source selection sensitive information
previously filed under a protective order to be included in the public
file. In Modern Technologies Corp. v. United States, 44 Fed. Cl.
319 (1998), a multiple contract award was made to five awardees that would
then compete for subsequent task orders. The award took place fourteen
months before the Court's decision to move the documents to the public
file. The Court held that because future task order negotiations would
reflect current conditions, rather than those when the award was announced,
the information covered by the protective order had minimal current value
and could be publicly released. Id. at 326. Thus, parties that participate
in a bid protest before the Court of Federal Claims face a risk that proprietary
information will ultimately be disclosed to their competitors.
V. DISCOVERY
The Court of Federal Claims provides an opportunity
for discovery that does not exist at the GAO. Like the GAO, the Court
requires the Government to prepare and produce the administrative record
without a specific request from the protester. The Court directs the government
to not only "identify and provide (or make available for inspection) the
administrative record" by a date set at the initial status conference,
but also "produce the core documents . . . as promptly as the circumstances
will permit." Gen. Order 38 õ 16. General Order No. 38 provides a list
of potential "core documents," but the list is neither exhaustive nor
mandatory. Gen. Order 38 õ 17. The General Order makes clear that the
required content of the administrative record should be decided by the
Court on a case-by-case basis. See Gen. Order 38 õ 19 annotation.
At the GAO, discovery is strictly limited to production
of documents. Although a party may request that the GAO review an agency's
decision to include or exclude certain documents from the record, see
4 C.F.R. Û 21.3 (c), (g) and (h), no further discovery is permissible.
The Court of Federal Claims, in contrast, has adopted the discovery standards
used in Administrative Procedure Act cases, such as Esch v. Yeutter,
876 F.2d 976 (D.C. Cir. 1989), which permit discovery beyond the administrative
record compiled by the Government in any of the following circumstances:
(1) when agency action is not adequately explained
in the record before the court; (2) when the agency failed to consider
factors which are relevant to its final decision; (3) when an agency
considered evidence which it failed to include in the record; (4)
when a case is so complex that a court needs more evidence to enable
it to understand the issues clearly; (5) in cases where evidence arising
after the agency action shows whether the decision was correct or
not; (6) in cases where agencies are sued for failure to take action;
(7) in cases arising using the National Environmental Policy Act;
and (8) in cases where relief is at issue, especially at the preliminary
injunction stage.
876 F.2d at 991. See Marine Hydraulics Int'l, Inc.
v. United States, 43 Fed. Cl. 664, 670-71 (1999).
To ensure the "whole" administrative record is properly
reviewed, the Court of Federal Claims has permitted the parties to take
depositions of the contracting officer. See Cubic Applications, Inc.
v. United States, 37 Fed. Cl. 339 (1997) (permitting consideration
of the contracting officer's post-award comments as "argument"). Furthermore,
in MVM, Inc. v. United States, 46 Fed. Cl. 126, 133-35 (2000),
the Court of Federal Claims allowed expert testimony to be admitted in
order to resolve a factual dispute regarding whether failure to amend
the contract improperly affected the pricing of the protester's proposal.
While supplementation of the record by the agency and experts regularly
occurs in GAO protests, there are no formal discovery procedures apart
from the production of records as part of the "agency report" and documents
requested by the protester. See 4 C.F.R. Û 21.3(c), (g), (h).
VI. STANDARD OF REVIEW
The Court of Federal Claims applies the standard of
review for agency action set forth in the Administrative Procedure Act,
5 U.S.C. Û 706. See 28 U.S.C. Û 1491(b)(4). A procurement decision
will be set aside only if the protester proves that the decision was "arbitrary,
capricious, an abuse of discretion, or otherwise not in accordance with
law." 5 U.S.C. Û 706(2)(A); see, e.g., Advanced Data Concepts, Inc.
v. United States, 43 Fed. Cl. 410, 416 (1999).
Recently, however, the Court of Appeals for the Federal
Circuit clarified that to prevail in a bid protest at the Court of Federal
Claims, the protester must also show that it was significantly prejudiced.
Earlier cases had suggested that if an agency's action was arbitrary and
capricious, or an abuse of discretion, then no showing of prejudice was
required. According to these cases, prejudice was required to be shown
only if the plaintiff alleged the agency's actions violated a procurement
statute or regulation. See Alfa Laval Separation, Inc. v. United States,
47 Fed. Cl. 305, 308 n.1 (2000). However, the Federal Circuit has now
stated without equivocation that "[t]o prevail in a bid protest, a protester
must show a significant, prejudicial error in the procurement process."
Alfa Laval Separation, Inc. v. United States, 175 F.3d 1365, 1367
(1999). To establish prejudice, the protester must show that, but for
the procurement error, there was a "substantial chance that [it] would
receive an award." Statistica, Inc. v. Christopher, 102 F.3d 1577,
1581 (Fed. Cir. 1996); see CACI, Inc.-Fed. v. United States, 719
F.2d 1567 (1574-75 (Fed. Cir. 1983).
There is somewhat less certainty at the Court of Federal
Claims because its judges are not required to follow their fellow judges'
decisions. Compare Day & Zimmermann Services v. United States,
38 Fed. Cl. 591 (1997) (Gibson, J.) (requiring "clear and convincing evidence"
of (1) a decision without rational basis, or (2) a clear and prejudicial
violation of applicable statutes or regulations), with R.R. Donnelly
& Sons, Co. v. United States, 38 Fed. Cl. 518 (1997) (Miller, J.)
(rejecting the convincing standard in favor of requiring a post-award
protester to meet a "high" burden of proof). See L. Kennedy & C.
Yukins, A Year of Progress: The New Federal Court Bid Protest Jurisdiction,
40 Government Contractor õ 40 (1998) at 3. In contrast, the standards
of review are more well-established at the GAO, even if the application
of those standards may vary among the Office of General Counsel "writing"
attorneys who prepare the initial drafts of the GAO's bid protest decisions.
VII. RECOVERY OF BID AND PROPOSAL COSTS
A post-award protester at the Court of Federal Claims
must be careful to make a claim for recovery of bid and proposal costs
separate and apart from its claim for injunctive relief seeking to overturn
the award. The Court recently explained why:
A
claim for proposal preparation costs is not a measure of damages for
an unlawful procurement, but, rather, an independent cause of action
with a different burden of proof. Plaintiff's position fails to recognize
that the legal standards for injunctive relieve and proposal preparation
costs are not identical. For injunctive relief plaintiff must demonstrate
arbitrary, capricious, or unreasonable action by the agency or action
that is in violation of a procurement statute or regulation that substantially
prejudices the offeror. See, e.g., Ellsworth Assocs., Inc. v. United
States, 45 Fed. Cl. 388, 392 (1999) (citing cases). The use of
the disjunctive "or" is of import. For recovery of proposal preparation
costs, plaintiff must demonstrate arbitrary, capricious, or unreasonable
actions. See E.W. Bliss Co. v. United States, 77 F.3d 445,
447 (Fed. Cir. 1996).
Alfa Laval Separation, Inc. v. United States,
47 Fed. Cl. 305, 311 (2000). In Alfa Laval, the protester failed
to include a claim for bid and proposal costs in its original complaint,
but sought them after the Federal Circuit had reversed and remanded the
Court of Federal Claims' initial decision denying the protest. The Court
of Federal Claims held that it was too late to seek bid and proposal costs,
because the protester had only proven that the agency's action was in
violation of procurement regulations, but had not shown it to be arbitrary,
capricious, or unreasonable. Id. at 311-14.
In contrast, at the GAO, award of bid and proposal
preparation costs may be made when a violation of procurement statutes
or regulations has been found, the protester was unreasonably excluded
from the competition and no other remedy is appropriate. See Nash,
supra at 854. This often occurs when contract performance has not
been suspended, or if the procurement is canceled by the agency. 4 CFR
Û 21.8(d)(2).
VIII. RECOVERY OF ATTORNEYS' FEES
The Court of Federal Claims may only grant attorney's fees
pursuant to the Equal Access to Justice Act. See Dubinsky v. United
States, 44 Fed. Cl. 360 (1999). Accordingly, attorney's fees will
only be available in actions filed in the Court of Federal Claims if the
prevailing party is an individual with net assets of less than 2 million
dollars or a firm with net assets of less than 7 million and 500 employees.
See Nash, supra at 891. The GAO may award any successful protester
the costs incurred in pursuing the protest, including reasonable attorneys'
fees. 4 C.F.R. Û 21.8(d). Protest costs are also recoverable at the GAO
if the agency takes corrective action in response to a protest and no
decision on the merits is issued by the GAO. See 4 C.F.R. Û 21.8(e).
IX. CONCLUSION
The Court of Federal Claims has provided new opportunities
for a post-award protester to file a protest after the short period for
filing at GAO expires. A protest action at the Court of Federal Claims
is also available after the GAO has issued a decision on the protest,
at which time the protester may obtain additional discovery from the agency.
These additional discovery opportunities are especially valuable because
they can be used after the protester has had time to fully review the
administrative record produced by the agency during GAO protester. Although
the Court of Federal Claims gives deference to the GAO's decision, see
Advanced Data Concepts, Inc. v. United States, 43 Fed. Cl. 410, 416
(1999), the opportunity for additional discovery and further refinement
of a protester's case make the Court of Federal Claims a valuable forum
in the appropriate case.
ABOUT THE AUTHORS
Allen Samelson is a shareholder in the Government
Contracts Practice Group and David Innis is special
counsel at Rogers, Joseph, O'Donnell & Quinn, San Francisco, California.
Copyright © Rogers, Joseph, O'Donnell & Quinn,
October 2000
Back to top
|